88Z AI, 25 November — According to Taiwan Commercial Times, NVIDIA’s AI chip supply remains tight, with significantly extended lead times for new orders of B300 and GB300 models. Workstation-grade super chipsets now face roughly 26-week waits. This production shift is squeezing consumer GPU availability, likely reducing GeForce RTX 50 series supply and slowing the rollout of the next-generation RTX 60 series.
At a glance
- Lead times for AI products like B300 and GB300 surge, with workstation chipsets facing ~26-week waits
- Production shifts reduce RTX 50 series supply and may slow the RTX 60 series launch
AI Chip Lead Times Extend Sharply
ODM manufacturers report that lead times for new orders of NVIDIA’s latest AI products, including the B300 and GB300, have increased substantially. Even workstation-grade super chipsets are facing delivery cycles of approximately 26 weeks, highlighting persistent bottlenecks amid surging demand for high-end AI computing power.
Consumer GPU Supply Under Pressure
The shift in production capacity toward AI solutions is further encroaching on resources for consumer graphics cards. Reports indicate that NVIDIA will reduce the supply of GeForce RTX 50 series gaming GPUs, and the rollout pace for the next-generation RTX 60 series may also slow down, leading to longer waits or higher acquisition barriers for gamers and general consumers.
Sources & editorial note
This article is an AI-assisted synthesis by 88Z AI based on the public sources below. Product claims and availability are attributed to their publishers. It does not represent independent testing or first-hand reporting.
- 36kr.comSource published
Source dates above refer to the original announcements; the date under the headline is this article’s publication on 88Z AI.